Aloha WB Ohana,
Be advised that Hawaiian Telcom is continuing to do construction work in Tower 2 by doing installation of the new cabling/wiring installs in the common areas and hallways only and they will now NOT need to access units during this initial phase. Hawaiian Telcom techs have already completed installs on floors 6-17 of Tower 2 so far and we anticipate finishing up to the 21st floor by Friday, 9/14.
Listed below will be the tentative schedule for next week and our Security/Assistant General Manager, Gilbert will continue to work closely with HT on daily work and schedules so we can keep everyone updated on the progress of this initial phase. (NOTE: This initial phase of installs will NOT affect your present cable service as service provider (Hawaiian Telcom) is just doing preliminary wiring/installations for our NEW system/network which will not start till 1/1/19)
- Monday, September 17th: Tower 2: 22nd & 23rd floors
- Tuesday, September 18th: Tower 2: 24th & 25th floors
- Wednesday, September 19th: Tower 2: 26th & 27th floors
- Thursday, September 20th: Tower 2: 28th & 29th floors
- Friday, September 21st: Tower 2: 30th & 31st floors
Please note that we are anticipating that HT techs will continue to be able to complete two (2) floors per day based on schedule but this may change depending on install factors and as we see the progress for this initial construction installs for our NEW system, we may adjust schedule as needed to facilitate a smooth process going forward. We will continue to send out notices for the next phase of floors that will be done as we work our way through each part of this process which will take a few months to complete.
We thank you for your patience and understanding. If you have any questions, please let us know.
Mahalo,
Sterling Paulos|General Manager