Aloha,
Please see below schedule for T1, Special Units Schedule. Demo must be completed by the demo date listed on the schedule to avoid any delays. It is highly recommended that the units listed be vacant especially for the units ending in 04/06 due to the extensive work that needs to be completed during the workday. The 04/06 stack will require the removal of the Vanity, Vanity Wall, Shower Wet Wall and Toilets to access the pipes for replacements. Therefore, it will not be functional during the project timeframe of the unit dates listed.
T1 Phase 2 Complete (as of 11.06.20)
T1-04&06, T2-03&05 Elevator Units
Mahalo,
AOAO Management Staff